FINAL
Former Hexagon Laboratories Site
BRONX COUNTY, NEW YORK
Site Management Plan
NYSDEC Site Number: 203003
Prepared for:
New York State Department of Environmental Conservation
625 Broadway
Albany, NY 12233-7013
Prepared by:
Ecology and Environment Engineering, P.C.
368 Pleasant View Drive
Lancaster, NY 14086
(716) 684-8060
Revisions to Final Approved Site Management Plan:
Revision # Submitted Date Summary of Revision DEC Approval Date
MARCH 2013
TABLE OF CONTENTS
TABLE OF CONTENTS ................................................................................................ II
LIST OF TABLES .......................................................................................................... VI
LIST OF FIGURES ........................................................................................................ VI
SITE MANAGEMENT PLAN ........................................................................................ 1
1.0 INTRODUCTION AND DESCRIPTION OF REMEDIAL PROGRAM ............ 1
1.1 INTRODUCTION....................................................................................................... 1
1.1.1 General ................................................................................................................... 1
1.1.2 Purpose ................................................................................................................... 2
1.1.3 Revisions ................................................................................................................ 3
1.2 SITE BACKGROUND ............................................................................................... 3
1.2.1 Site Location and Description ................................................................................ 3
1.2.2 Site History ............................................................................................................. 3
1.2.3 Geologic Conditions ............................................................................................... 5
1.3 SUMMARY OF REMEDIAL INVESTIGATION FINDINGS ............................. 6
1.4 SUMMARY OF REMEDIAL ACTIONS .............................................................. 13
1.4.1 OU-1 Soils ............................................................................................................ 13
1.4.2 OU-2 Groundwater ............................................................................................... 14
1.4.3 Site-Related Treatment Systems .......................................................................... 17
1.4.4 Remaining Contamination .................................................................................... 17
ii
2.0 ENGINEERING AND INSTITUTIONAL CONTROL PLAN ............................ 19
2.1 INTRODUCTION..................................................................................................... 19
2.1.1 General ................................................................................................................. 19
2.1.2 Purpose ................................................................................................................. 19
2.2 ENGINEERING CONTROLS ................................................................................ 20
2.2.1 Engineering Control Systems ............................................................................... 20
2.2.2 Criteria for Completion of Remediation/Termination of Remedial Systems ...... 20
2.3 INSTITUTIONAL CONTROLS ............................................................................. 21
2.3.1 Excavation Work Plan .......................................................................................... 23
2.4 INSPECTIONS AND NOTIFICATIONS .............................................................. 24
2.4.1 Inspections ............................................................................................................ 24
2.4.2 Notifications ......................................................................................................... 24
2.5 CONTINGENCY PLAN .......................................................................................... 25
2.5.1 Emergency Telephone Numbers .......................................................................... 26
2.5.2 Map and Directions to Nearest Health Facility .................................................... 26
2.5.3 Response Procedures ............................................................................................ 28
3.0 SITE MONITORING PLAN ................................................................................... 29
3.1 INTRODUCTION..................................................................................................... 29
3.1.1 General ................................................................................................................. 29
3.1.2 Purpose and Schedule........................................................................................... 29
3.2 SOIL COVER SYSTEM MONITORING ............................................................. 30
3.3 MEDIA MONITORING PROGRAM .................................................................... 30
3.3.1 Groundwater Monitoring...................................................................................... 31
iii
3.4 SITE-WIDE INSPECTION ..................................................................................... 33
3.5 MONITORING QUALITY ASSURANCE/QUALITY CONTROL ................... 33
3.6 MONITORING REPORTING REQUIREMENTS .............................................. 34
4.0 OPERATION AND MAINTENANCE PLAN ....................................................... 36
4.1 INTRODUCTION..................................................................................................... 36
5.0 INSPECTIONS, REPORTING AND CERTIFICATIONS .................................. 37
5.1 SITE INSPECTIONS ............................................................................................... 37
5.1.1 Inspection Frequency ........................................................................................... 37
5.1.2 Inspection Forms, Sampling Data, and Maintenance Reports ............................. 37
5.1.3 Evaluation of Records and Reporting .................................................................. 37
iv